Which of these is not one of the phenomenons likely to occur while the phase I application of SPC?

Which of these is not one of the phenomenons likely to occur while the phase I application of SPC? Correct Answer Process changing its state continuously between in-control and out-of-control

Shewhart control charts are used in phase I implementation of the SPC, where process is likely to be out-of-control, and experiencing assignable causes, which may result in large shifts in the monitored parameters.