There are four stages of FMEA. i) Specifyingthe possibilities ii) Quantifying risk iii) Correcting high risk causes iv) Re-evaluation of Risk Which is the correct order of proceeding with these stages of FMEA?
There are four stages of FMEA. i) Specifyingthe possibilities ii) Quantifying risk iii) Correcting high risk causes iv) Re-evaluation of Risk Which is the correct order of proceeding with these stages of FMEA? Correct Answer i),ii),iii),iv)
The correct order of proceeding is by first specifying possibilities. It is followed by quantification of risk. Correcting high risk causes and re-evaluation of risk follows next. The re-evaluation of risk involves the recalculation of the risk priority number (RPN).