As labor costs, an electrician charges TK. 36.50 per hour for himself and TK. 27.50 per hour for his assistant . What would be the total labor cost for a job taking 61 hours ?
As labor costs, an electrician charges TK. 36.50 per hour for himself and TK. 27.50 per hour for his assistant . What would be the total labor cost for a job taking 61 hours ? Correct Answer TK. 4160.00
Cost per hour = 36.50 + 27.50 = 64 TK. Total cost = 64×61 = 3904 TK